Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 9.8 | 0 | 0 | 0 |
34W44 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनोदेश संख्या 2454/2 05 प्रा0 आ0/05 पी0सी0 लो0नि0 अनु0 2 दिनांक 28.10.2005
TS Amount (lakhs) : 119 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
119.00
Resanction Cost :
119.00
Tentative Cost :
119.00
Exp. Upto Last Fy : 109.60
For CFY 2024-2025
Remaining : 9.40
Demand : 9.40
Allotment : 9.35
Exp in CFY : 9.35
Total Up to Date Exp : 118.95
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
18 years 8 months ago
28 Oct 2005
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
3 months 3 weeks ago
23 Mar 2024
Remark
Forest Status 15: AIP Nodal
Bottelneck: no issue
work complete. -- as on 23-Mar-2024
Physical Peramenters