Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3 | 0 | ||
Span of Bridges [m] | 1 | 1 | 1 | 0 |
34W461 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 2195/।।।(2)/13-14 (प्रा0आ0) /2012 दिनांक 22.3.2013
TS Amount (lakhs) : 43.5 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
43.50
Resanction Cost :
43.50
Tentative Cost :
43.50
Exp. Upto Last Fy : 10.76
For CFY 2024-2025
Remaining : 32.74
Demand : 5.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 10.76
Work completed
Physical Progress:
At start of FY 2024-2025 : 5 %
Up to Date : 80 %
Sanction on :
11 years 3 months ago
22 Mar 2013
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 10: In Principal approval
Bottelneck: no issue
सैद्धान्तिक स्वीकृति प्राप्त। अतिरिक्त एन0पी0वी0 का भुगतान पूर्ण। अनुपालन आख्या प्रभागीय वनाधिकारी बड़कोट को प्रेषित। -- as on 14-Apr-2023
Physical Peramenters