Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 6 | 6 | 6 | 0 |
34W68 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 2952/।।।(2)/16-59 (प्रा0आ0)/2005 टी0सी0-1 दिनांक 9.11.2016
TS Amount (lakhs) : 350.43 Lacs
Financial Detail
Sanction Cost : 94.80 Lacs
Resanction Cost : 350.43 Lacs
Exp. Upto Last Fy : 195.31 Lacs
For CFY 2024-2025
Remaining : 155.12 Lacs
Demand : 100.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 195.31 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 60 %
Up to Date : 60 %
Sanction on :
7 years 6 months ago
09 Nov 2016
Tentative Completion date:
1 year 7 months from now
31 Dec 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 18: Final Approval
Bottelneck: no issue
scupper and walling work in progress in km 3,4,5and 6. -- as on 01-Mar-2024
Physical Peramenters