Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 6 | 6 | 4.000 | 2 | 0.000 | 0.000 |
34W68 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 2952/।।।(2)/16-59 (प्रा0आ0)/2005 टी0सी0-1 दिनांक 9.11.2016
TS Amount (lakhs) : 350.43 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
94.80
Resanction Cost :
350.43
Tentative Cost :
350.43
Exp. Upto Last Fy : 195.31
For CFY 2024-2025
Remaining : 155.12
Demand : 100.00
Allotment : 0.00
Exp in CFY : 1.75
Total Up to Date Exp : 197.06
Construction Started
Physical Progress:
At start of FY 2024-2025 : 60 %
Up to Date : 80 %
Sanction on :
7 years 8 months ago
09 Nov 2016
Tentative Completion date:
1 year 5 months from now
31 Dec 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 18: Final Approval
Bottelneck: no issue
part II work in completion stage .minor work remaining. -- as on 29-Jun-2024
Physical Peramenters