Work Profile

34W68 :

No Pic Avilable Time series Gantt
कुथनोर से हलना मोटर मार्ग का नाम शहीद सुभाष चन्द के मोटर मार्ग।


Work not linked with IM

Bridges on The Basis of AI:

Administrative Approval Detail : शासनादेश संख्या 2952/।।।(2)/16-59 (प्रा0आ0)/2005 टी0सी0-1 दिनांक 9.11.2016

TS Amount (lakhs) : 350.43 Lacs

Financial Detail (in Rs Lakhs)

Sanction Cost :

94.80

Resanction Cost :

350.43

Tentative Cost :

350.43

Exp. Upto Last Fy : 195.31

For CFY 2024-2025

Remaining : 155.12

Demand : 100.00

Allotment : 0.00

Exp in CFY : 1.75

Total Up to Date Exp : 197.06

Construction Started

Physical Progress:

At start of FY 2024-2025 : 60 %

Up to Date : 80 %

Sanction on :
7 years 8 months ago
09 Nov 2016


Tentative Completion date:
1 year 5 months from now
31 Dec 2025


Actual Completion Date:
Not Yet Reported


Rating : 116

Remark

Forest Status 18: Final Approval

Bottelneck: no issue


part II work in completion stage .minor work remaining. -- as on 29-Jun-2024

Physical Peramenters

Particulars Sanction Resanction Upto Last Fy For Cfy 2024-2025
Remaining Target Achievement
Length of Road [Km] 6 6 4.000 2 0.000 0.000