Work Profile Report [34W68]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : शासनादेश संख्या 2952/।।।(2)/16-59 (प्रा0आ0)/2005 टी0सी0-1 दिनांक 9.11.2016
TS Amount (lakhs) : 350.43 Lacs
Budget Financial Head : SCSP ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
94.80
Resanction Cost :
350.43
Tentative Cost :
350.43
Exp. Upto Last Fy :
195.31
For CFY 2024-2025
Remaining :
155.12
Demand :
100.00
Allotment :
30.00
Exp in CFY :
42.02
Total Up to Date Exp :
237.33
Construction Started
Sanction on : 8 years 2 weeks ago
09 Nov 2016
Physical Progress:
At start of FY 2024-2025 :
60 %
Up to Date :
80 %
Tentative Completion date on : 1 year 1 month from now
31 Dec 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
part II work in completion stage .minor work remaining. -- as on 29-Jun-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: