Work Profile Report [34W68]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : शासनादेश संख्या 2952/।।।(2)/16-59 (प्रा0आ0)/2005 टी0सी0-1 दिनांक 9.11.2016
TS Amount (lakhs) : 350.43 Lacs
Budget Financial Head : SCSP ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
94.80
Resanction Cost :
350.43
Tentative Cost :
350.43
Exp. Upto Last Fy :
296.66
For CFY 2025-2026
Remaining :
53.77
Demand :
53.77
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
296.66
Work completed
Sanction on : 8 years 5 months ago
09 Nov 2016
Physical Progress:
At start of FY 2025-2026 :
95 %
Up to Date :
95 %
Tentative Completion date on : 8 months 2 days from now
31 Dec 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
विधिवत स्वीकृति प्राप्त। कार्य पूर्ण। -- as on 23-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: