Work Profile

कुथनोर से हलना मोटर मार्ग का नाम शहीद सुभाष चन्द के मोटर मार्ग।


Work not linked with IM

Bridges on The Basis of AI:

Administrative Approval Detail : शासनादेश संख्या 2952/।।।(2)/16-59 (प्रा0आ0)/2005 टी0सी0-1 दिनांक 9.11.2016

TS Amount (lakhs) : 350.43 Lacs

Financial Detail

Sanction Cost : 94.80 Lacs

Resanction Cost : 350.43 Lacs

Exp. Upto Last Fy : 195.31 Lacs

For CFY 2024-2025

Remaining : 155.12 Lacs

Demand : 100.00 Lacs

Allotment : 0.00 Lacs

Exp in CFY : 0.00 Lacs

Total Up to Date Exp : 195.31 Lacs

Construction Started

Physical Progress:

At start of FY 2024-2025 : 60 %

Up to Date : 60 %

Sanction on :
7 years 6 months ago
09 Nov 2016


Tentative Completion date:
1 year 7 months from now
31 Dec 2025


Actual Completion Date:
Not Yet Reported


Rating : 90

Remark

Forest Status 18: Final Approval

Bottelneck: no issue


scupper and walling work in progress in km 3,4,5and 6. -- as on 01-Mar-2024

Physical Peramenters

Particulars Sanction Resanction Upto Last Fy For Cfy 2024-2025
Remaining Target Achievement
Length of Road [Km] 6 6 6 0
Currently only Bank Gaurantee information is avilable