Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 6 | 0 | 0 | 0 |
34W915 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 957/।।।(2)/21-02(एम0एल0ए0)/2017 दिनांक 31.03.2021
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
77.64
Resanction Cost :
77.64
Tentative Cost :
77.64
Exp. Upto Last Fy : 2.09
For CFY 2024-2025
Remaining : 75.55
Demand : 5.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 2.09
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 50 %
Sanction on :
3 years 3 months ago
31 Mar 2021
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 04: DFO
Bottelneck: no issue
forest proposal made. joint inspection with dfo completed on 12/07/2024 for removal of EDS. -- as on 12-Jul-2024
Physical Peramenters