Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.3 | 2.3 | 2.3 | 0 |
34W956 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 1698/।।।(2)/21-01(एम0एल0ए0)/2017 टी.सी. दिनांक 16.06.2021
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
21.32
Resanction Cost :
21.32
Tentative Cost :
21.32
Exp. Upto Last Fy : 4.60
For CFY 2024-2025
Remaining : 16.72
Demand : 2.50
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 4.60
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 50 %
Sanction on :
3 years 1 month ago
16 Jun 2021
Tentative Completion date:
2 years 3 months ago
31 Mar 2022
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
2nd phase DPR (stage 1) sent to Sachiv PWD Uttarakhand Shasan by letter no- 8030/06(34) yata0-star-I(Zonal Office)/2023 date 12/12/2023, Amt=79.01lac, Length=2.30km -- as on 18-Dec-2023
Physical Peramenters