Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 7 | 7 | 7 | 0 |
34W971 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 6588/।।।(2)/21-02(एम0एल0ए0)/2017 टी0सी0 दिनांक 31.12.2021
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
57.96
Resanction Cost :
57.96
Tentative Cost :
57.96
Exp. Upto Last Fy : 0.08
For CFY 2024-2025
Remaining : 57.88
Demand : 5.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.08
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 50 %
Sanction on :
2 years 6 months ago
31 Dec 2021
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
समरेखण प्रस्ताव अनुमोदित। -- as on 06-Jun-2024
Physical Peramenters