Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3 | 0 |
36W151 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : श्शासनादेश संख्या 2970 (1)/।।। (2)/11-10 (मु.मं.घो.) /2011 दिनांक 15 जुलाई 2011
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 37.80 Lacs
Resanction Cost : 37.80 Lacs
Exp. Upto Last Fy : 4.56 Lacs
For CFY 2024-2025
Remaining : 33.24 Lacs
Demand : 30.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 4.56 Lacs
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
12 years 10 months ago
15 Jul 2011
Tentative Completion date:
2 months 1 week from now
31 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 10: In Principal approval
Bottelneck: no issue
द्वितीय चरण (स्टेज-1) की स्वीकृति शासन की ई-फाईल संख्या 49189 दिनांक 24.08.2023 द्वारा प्राप्त। -- as on 29-Sep-2023
Physical Peramenters