Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3 | 0 |
36W151 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : श्शासनादेश संख्या 2970 (1)/।।। (2)/11-10 (मु.मं.घो.) /2011 दिनांक 15 जुलाई 2011
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
37.80
Resanction Cost :
37.80
Tentative Cost :
37.80
Exp. Upto Last Fy : 4.56
For CFY 2024-2025
Remaining : 33.24
Demand : 30.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 4.56
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
13 years 2 days ago
15 Jul 2011
Tentative Completion date:
1 week 6 days from now
31 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 13: AIP DFO
Bottelneck: no issue
द्वितीय चरण (स्टेज-1) की स्वीकृति शासन की ई-फाईल संख्या 49189 दिनांक 24.08.2023 द्वारा प्राप्त। -- as on 29-Sep-2023
Physical Peramenters