Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1 | 0.875 | 0.875 | 0 |
36W223 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 13/।।। (2)/15-01 (प्रा॰आ॰)/2015 दिनांक 11 फरवरी 2015
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
17.55
Resanction Cost :
17.55
Tentative Cost :
17.55
Exp. Upto Last Fy : 16.20
For CFY 2024-2025
Remaining : 1.35
Demand : 1.35
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 16.20
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
9 years 5 months ago
11 Feb 2015
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 01: Withdraw
Bottelneck: no issue
शासनादेश संख्या 1246/।।।ृ(2)/19-05(एम॰एल॰ए॰)/2017 टी॰सी॰ दिनांक 6 मार्च, 2019 द्वारा द्वितीय चरण की स्वीकृति प्राप्त। द्वितीय चरण का कार्य पूर्ण। मुआवजा भुगतान किया जा रहा है। -- as on 31-Mar-2024
Physical Peramenters