Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 9 | 9.875 | 0.000 | 9.875 | 0.000 | 0.000 |
36W231 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा॰सं॰ 2724/।।।(2) /15-05 (मु॰मं॰घो॰)/ 2015 दि॰ 23.4.2015
TS Amount (lakhs) : 10.38 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
125.55
Resanction Cost :
125.55
Tentative Cost :
125.55
Exp. Upto Last Fy : 5.45
For CFY 2024-2025
Remaining : 120.10
Demand : 0.18
Allotment : 0.18
Exp in CFY : 0.18
Total Up to Date Exp : 5.63
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
9 years 2 months ago
23 Apr 2015
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 01: Withdraw
Bottelneck: Other Reason
आख्या दिनांक 16.04.2024 को प्राप्त। उपलब्ध करायी गयी भूमि के डिजिटल मैप तैयार करवाये जा रहे है। -- as on 01-May-2024
Physical Peramenters