Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 4.275 | 4.275 | 0 |
36W233 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 4886/।।।(2)/15-10(मु॰मं॰घो॰)/2015 दिनांक 22.07.2015
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 59.00 Lacs
Resanction Cost : 59.00 Lacs
Exp. Upto Last Fy : 44.62 Lacs
For CFY 2024-2025
Remaining : 14.38 Lacs
Demand : 10.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 44.62 Lacs
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
8 years 9 months ago
22 Jul 2015
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: Alignment Dispute
प्रतिकर भुगतान की कार्यवाही गतिमान है। -- as on 31-Oct-2023
Physical Peramenters