Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 15 | 15.4 | 15.4 | 0 | ||
No of Bridges | 2 | 2 | 2 | 0 |
36W329 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 5861/।।।(2)/18-05(एम॰एल॰ए॰)/2017 दिनांक 04 दिसम्बर 2018
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 271.32 Lacs
Resanction Cost : 271.32 Lacs
Exp. Upto Last Fy : 13.22 Lacs
For CFY 2024-2025
Remaining : 258.10 Lacs
Demand : 5.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 13.22 Lacs
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
5 years 5 months ago
04 Dec 2018
Tentative Completion date:
1 year 7 months from now
31 Dec 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 06: Conservator
Bottelneck: Other Reason
वृक्षों की गणना दिनांक 29.02.2024 को पूर्ण। आख्या दिनांक 12.04.2024 को प्राप्त। -- as on 01-May-2024
Physical Peramenters