Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 8 | 5.825 | 5.825 | 0 |
36W352 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 237/।।।(2)/20-5(एम॰एल॰ए॰)2017 दिनांक 10 जनवरी, 2020
TS Amount (lakhs) : 10.67 Lacs
Financial Detail
Sanction Cost : 179.97 Lacs
Resanction Cost : 179.97 Lacs
Exp. Upto Last Fy : 0.49 Lacs
For CFY 2024-2025
Remaining : 179.48 Lacs
Demand : 1.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.49 Lacs
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
4 years 4 months ago
10 Jan 2020
Tentative Completion date:
1 year 5 months from now
31 Oct 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 02: Division
Bottelneck: no issue
दोगुने क्षेत्रफल का उपयुक्तता प्रमाण पत्र दिनांक 15.04.2024 को प्राप्त। डिजिटल मैप तैयार करवाये जा रहे है। -- as on 01-May-2024
Physical Peramenters