Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 4.800 | 0.2 | 0.200 | 0.000 |
36W381 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 955(1)/।।।(2)/21-05(एम॰एल॰ए॰)/2017टी॰सी॰-।।। दिनांक 31 मार्च, 2021
TS Amount (lakhs) : 220.06 Lacs
Financial Detail
Sanction Cost : 220.06 Lacs
Resanction Cost : 220.06 Lacs
Exp. Upto Last Fy : 192.28 Lacs
For CFY 2024-2025
Remaining : 27.78 Lacs
Demand : 27.78 Lacs
Allotment : 20.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 192.28 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 90 %
Sanction on :
3 years 1 month ago
31 Mar 2021
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
शासन के कार्यालय ज्ञाप संख्या 1346(1)/।।।(2)/21-5 (एम॰एल॰ए॰)/2017 टी॰सी॰।।। दिनांक 17.05.2021 द्वारा मार्ग को डेढ़ लेन किये जाने हेतु उक्त कार्य संशोधित किया गया है। मार्ग चैड़ीकरण का कार्य प्रगति में। -- as on 30-Jan-2023
Physical Peramenters