Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5 | 0 | ||
No of Bridges | 2 | 2 | 2 | 0 |
36W400 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 5303/।।।(2)/21-05 (एम॰एल॰ए॰)/ 2017 टी॰सी॰।। दिनांक 01 नवम्बर, 2021
TS Amount (lakhs) : 6.64 Lacs
Financial Detail
Sanction Cost : 83.70 Lacs
Resanction Cost : 83.70 Lacs
Exp. Upto Last Fy : 2.30 Lacs
For CFY 2024-2025
Remaining : 81.40 Lacs
Demand : 1.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 2.30 Lacs
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
2 years 6 months ago
01 Nov 2021
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 01: Withdraw
Bottelneck: Other Reason
लैण्ड शैड्यूल तैयार किया जा रहा है। -- as on 29-Feb-2024
Physical Peramenters