Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 5.000 | 0.000 |
36W402 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 505(1)/।।।(2)/22-05 (एम॰एल॰ए॰)/2017 टी॰सी॰-। दिनांक 07 जनवरी, 2022
TS Amount (lakhs) : 464.19 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
472.57
Resanction Cost :
464.19
Tentative Cost :
464.19
Exp. Upto Last Fy : 291.00
For CFY 2024-2025
Remaining : 173.19
Demand : 150.00
Allotment : 60.00
Exp in CFY : 47.23
Total Up to Date Exp : 338.23
Construction Started
Physical Progress:
At start of FY 2024-2025 : 65 %
Up to Date : 90 %
Sanction on :
2 years 6 months ago
07 Jan 2022
Tentative Completion date:
5 months 1 week from now
31 Dec 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
अतिरिक्त पहाड़ कटान, स्कपर निर्माण एवं पी॰सी॰ कार्य पूर्ण। नाली निर्माण कार्य प्रगति में। -- as on 01-Jul-2024
Physical Peramenters