Work Profile Report [36W402]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश संख्या 505(1)/।।।(2)/22-05 (एम॰एल॰ए॰)/2017 टी॰सी॰-। दिनांक 07 जनवरी, 2022
TS Amount (lakhs) : 464.19 Lacs
Budget Financial Head : SCSP ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
472.57
Resanction Cost :
464.19
Tentative Cost :
464.19
Exp. Upto Last Fy :
291.00
For CFY 2024-2025
Remaining :
173.19
Demand :
150.00
Allotment :
150.00
Exp in CFY :
139.51
Total Up to Date Exp :
430.51
Construction Started
Sanction on : 2 years 10 months ago
07 Jan 2022
Physical Progress:
At start of FY 2024-2025 :
65 %
Up to Date :
90 %
Tentative Completion date on : 1 month 1 week from now
31 Dec 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
अतिरिक्त पहाड़ कटान, स्कपर निर्माण एवं पी॰सी॰ कार्य पूर्ण। नाली निर्माण एवं दीवार निर्माण कार्य प्रगति में। -- as on 05-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: