Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 1.775 | 1.775 | 0 |
36W426 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासन की ई-फाईल संख्या 45257 दिनांक 13.02.2023
TS Amount (lakhs) : 3.75 Lacs
Financial Detail
Sanction Cost : 3.00 Lacs
Resanction Cost : 3.00 Lacs
Exp. Upto Last Fy : 0.27 Lacs
For CFY 2024-2025
Remaining : 2.73 Lacs
Demand : 1.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.27 Lacs
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
1 year 3 months ago
13 Feb 2023
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 03: DM
Bottelneck: no issue
लैण्ड शॅड्यूल तैयार किया जा रहा है। -- as on 29-Feb-2024
Physical Peramenters