Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5 | 0 |
36W430 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासन की ई-फाईल संख्या 48849 दिनांक 21 मार्च 2023
TS Amount (lakhs) : 7.5 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
7.50
Resanction Cost :
7.50
Tentative Cost :
7.50
Exp. Upto Last Fy : 0.53
For CFY 2024-2025
Remaining : 6.97
Demand : 2.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.53
Survey work done
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
1 year 3 months ago
21 Mar 2023
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 01: Withdraw
Bottelneck: no issue
आपत्तियों के निराकरण हेतु पुनः सर्वेक्षण कार्य दिनांक 29.04.2024 को पूर्ण। -- as on 01-May-2024
Physical Peramenters