Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 1 | 0 | 0 | 0 |
36W439 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : मुख्य विकास अधिकारी,चमोली के पत्रांक 225/जि॰यो॰/2023-24 दिनांक 01 जून 2023 द्वारा
TS Amount (lakhs) : 7.5 Lacs
Financial Detail
Sanction Cost : 7.50 Lacs
Resanction Cost : 7.50 Lacs
Exp. Upto Last Fy : 5.49 Lacs
For CFY 2024-2025
Remaining : 2.01 Lacs
Demand : 2.00 Lacs
Allotment : 0.01 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 5.49 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
11 months 2 weeks ago
01 Jun 2023
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्वों का भुगतान शेष। -- as on 30-Mar-2024
Physical Peramenters