Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.2 | 1.2 | 0.350 | 0.85 | 0.850 | 0.000 |
36W447 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासन की ई-फाईल संख्या 53969 दिनांक 03.08.2023
TS Amount (lakhs) : 39.55 Lacs
Financial Detail
Sanction Cost : 39.55 Lacs
Resanction Cost : 39.55 Lacs
Exp. Upto Last Fy : 9.25 Lacs
For CFY 2024-2025
Remaining : 30.30 Lacs
Demand : 30.30 Lacs
Allotment : 10.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 9.25 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 40 %
Sanction on :
9 months 2 weeks ago
03 Aug 2023
Tentative Completion date:
2 weeks 3 days ago
02 May 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य का अनुबन्ध गठित। पहाड़ कटान एवं मक डम्पिंग का कार्य प्रगति में। -- as on 30-Nov-2023
Physical Peramenters