Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 0.300 | 2.7 | 2.700 | 0.000 |
36W449 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासन की ई-फाईल संख्या 49189 दिनांक 24.08.2023 द्वारा प्राप्त।
TS Amount (lakhs) : 138.59 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
138.59
Resanction Cost :
138.59
Tentative Cost :
138.59
Exp. Upto Last Fy : 28.20
For CFY 2024-2025
Remaining : 110.39
Demand : 110.39
Allotment : 40.00
Exp in CFY : 21.43
Total Up to Date Exp : 49.63
Construction Started
Physical Progress:
At start of FY 2024-2025 : 30 %
Up to Date : 70 %
Sanction on :
10 months 3 weeks ago
24 Aug 2023
Tentative Completion date:
3 months 1 day from now
19 Oct 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पहाड़ कटान एवं मक डम्पिंग का कार्य प्रगति में। -- as on 15-Jan-2024
Physical Peramenters