Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
No of Bridges | 1 | 1 | 1 | 0 | ||
Span of Bridges [m] | 30 | 30 | 30 | 0 |
36W454 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासन की ई-फाईल संख्या 26616 एवं कम्प्यूटर जनित संख्या 163736/2023 दिनांक 23.10.2023
TS Amount (lakhs) : 3.6 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
3.60
Resanction Cost :
3.60
Tentative Cost :
3.60
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 3.60
Demand : 1.50
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.00
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
8 months 3 weeks ago
23 Oct 2023
Tentative Completion date:
3 months 1 week from now
31 Oct 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 01: Withdraw
Bottelneck: no issue
संयुक्त निरीक्षण किये जाने हेतु खण्ड के पत्रांक 1061/10एल॰ए॰ दिनांक 29.05.2024 द्वारा उपजिलाधिकारी चमोली को पत्र प्रेषित। -- as on 01-Jul-2024
Physical Peramenters