Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 11 | 11 | 0.000 | 11 | 11.000 | 0.000 |
36W459 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासन की ई-फाईल संख्या 48456 एवं कम्प्यूटर जनित संख्या 185624/2024 दिनांक 30.01.2024
TS Amount (lakhs) : 151.7 Lacs
Financial Detail
Sanction Cost : 151.70 Lacs
Resanction Cost : 151.70 Lacs
Exp. Upto Last Fy : 4.99 Lacs
For CFY 2024-2025
Remaining : 146.71 Lacs
Demand : 146.71 Lacs
Allotment : 70.00 Lacs
Exp in CFY : 33.40 Lacs
Total Up to Date Exp : 38.39 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 45 %
Up to Date : 45 %
Sanction on :
3 months 2 weeks ago
30 Jan 2024
Tentative Completion date:
9 months 2 weeks from now
04 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
दीवार निर्माण एवं पी॰सी॰ द्वारा डामरीकरण का कार्य प्रगति में। -- as on 01-May-2024
Physical Peramenters