Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 11 | 11 | 0.000 | 11 | 11.000 | 0.000 |
36W459 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासन की ई-फाईल संख्या 48456 एवं कम्प्यूटर जनित संख्या 185624/2024 दिनांक 30.01.2024
TS Amount (lakhs) : 151.7 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
151.70
Resanction Cost :
151.70
Tentative Cost :
151.70
Exp. Upto Last Fy : 4.99
For CFY 2024-2025
Remaining : 146.71
Demand : 146.71
Allotment : 78.87
Exp in CFY : 78.01
Total Up to Date Exp : 83.01
Construction Started
Physical Progress:
At start of FY 2024-2025 : 45 %
Up to Date : 65 %
Sanction on :
5 months 2 weeks ago
30 Jan 2024
Tentative Completion date:
7 months 2 weeks from now
04 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पी॰सी॰ द्वारा डामरीकरण कार्य पूर्ण। दीवार निर्माण कार्य प्रगति में। -- as on 25-Jun-2024