Work Profile Report [36W460]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : शासन की ई-फाईल संख्या 48456 एवं कम्प्यूटर जनित संख्या 185624/2024 दिनांक 30.01.2024
TS Amount (lakhs) : 215.62 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
215.62
Resanction Cost :
215.62
Tentative Cost :
215.62
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
215.62
Demand :
215.62
Allotment :
215.62
Exp in CFY :
208.91
Total Up to Date Exp :
208.91
Construction Started
Sanction on : 10 months 3 weeks ago
30 Jan 2024
Physical Progress:
At start of FY 2024-2025 :
15 %
Up to Date :
51 %
Tentative Completion date on : 2 months 1 week from now
05 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
दीवार निर्माण एवं पी॰सी॰ कार्य प्रगति में। -- as on 05-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand