Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 10.84 | 10.84 | 0.000 | 10.84 | 10.840 | 0.000 |
36W460 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासन की ई-फाईल संख्या 48456 एवं कम्प्यूटर जनित संख्या 185624/2024 दिनांक 30.01.2024
TS Amount (lakhs) : 215.62 Lacs
Financial Detail
Sanction Cost : 215.62 Lacs
Resanction Cost : 215.62 Lacs
Exp. Upto Last Fy : 0.00 Lacs
For CFY 2024-2025
Remaining : 215.62 Lacs
Demand : 215.62 Lacs
Allotment : 80.00 Lacs
Exp in CFY : 14.10 Lacs
Total Up to Date Exp : 14.10 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 15 %
Up to Date : 15 %
Sanction on :
3 months 2 weeks ago
30 Jan 2024
Tentative Completion date:
9 months 2 weeks from now
05 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य की निविदा निस्तारित कर दिनांक 06.03.2024 को अनुबन्ध गठित। दीवार निर्माण कार्य प्रगति में। -- as on 30-Mar-2024
Physical Peramenters