36W460 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासन की ई-फाईल संख्या 48456 एवं कम्प्यूटर जनित संख्या 185624/2024 दिनांक 30.01.2024
TS Amount (lakhs) : 215.62 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
215.62
Resanction Cost :
215.62
Tentative Cost :
215.62
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 215.62
Demand : 215.62
Allotment : 45.85
Exp in CFY : 45.85
Total Up to Date Exp : 45.85
Construction Started
Physical Progress:
At start of FY 2024-2025 : 15 %
Up to Date : 45 %
Sanction on :
5 months 2 weeks ago
30 Jan 2024
Tentative Completion date:
7 months 2 weeks from now
05 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पी॰सी॰ द्वारा डामरीकरण का कार्य प्रगति में। -- as on 13-Jun-2024