Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 0.000 | 2 | 0.000 | 0.000 |
37W102 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 7034/।।।(2)/10-41 (एम0एल0ए0)/2010 दिनांक 19/2/2011
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
25.20
Resanction Cost :
25.20
Tentative Cost :
25.20
Exp. Upto Last Fy : 6.10
For CFY 2024-2025
Remaining : 19.10
Demand : 5.00
Allotment : 5.00
Exp in CFY : 0.00
Total Up to Date Exp : 6.10
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
13 years 4 months ago
19 Feb 2011
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
6 years 3 months ago
01 Apr 2018
Remark
Forest Status 18: Final Approval
Bottelneck: no issue
मुआवजा भुगतान प्रस्ताव गठित, राजस्व विभाग से सत्यापन होना है। -- as on 23-Dec-2023
Physical Peramenters