Work Profile Report [37W105]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 7034/।।।(2)/10-41 (एम0एल0ए0)/2010 दिनांक 19/2/2011
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
25.20
Resanction Cost :
25.20
Tentative Cost :
25.20
Exp. Upto Last Fy :
1.28
For CFY 2024-2025
Remaining :
23.92
Demand :
1.00
Allotment :
0.50
Exp in CFY :
0.31
Total Up to Date Exp :
1.58
Alignment Approved
Sanction on : 13 years 10 months ago
19 Feb 2011
Physical Progress:
At start of FY 2024-2025 :
20 %
Up to Date :
20 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
प्रतिकर प्रस्ताव गठित किया जा रहा है। -- as on 20-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: