Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 0.000 | 2 | 0.000 | 0.000 |
37W105 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 7034/।।।(2)/10-41 (एम0एल0ए0)/2010 दिनांक 19/2/2011
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 25.20 Lacs
Resanction Cost : 25.20 Lacs
Exp. Upto Last Fy : 1.28 Lacs
For CFY 2024-2025
Remaining : 23.92 Lacs
Demand : 1.00 Lacs
Allotment : 1.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 1.28 Lacs
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 20 %
Up to Date : 20 %
Sanction on :
13 years 3 months ago
19 Feb 2011
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 13: AIP DFO
Bottelneck: no issue
प्रतिकर प्रस्ताव गठित किया जाना है। -- as on 23-Dec-2023
Physical Peramenters