Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 0.000 | 2 | 0.000 | 0.000 |
37W108 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 7034/।।।(2)/10-41 (एम0एल0ए0)/2010 दिनांक 19/2/2011
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
25.20
Resanction Cost :
25.20
Tentative Cost :
25.20
Exp. Upto Last Fy : 23.64
For CFY 2024-2025
Remaining : 1.56
Demand : 0.42
Allotment : 0.42
Exp in CFY : 0.03
Total Up to Date Exp : 23.68
Work completed
Physical Progress:
At start of FY 2024-2025 : 95 %
Up to Date : 95 %
Sanction on :
13 years 4 months ago
19 Feb 2011
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 20: Kattan
Bottelneck: no issue
नाबार्ड 24 के अन्तर्गत कार्य पूर्ण कर लिया गया हैै। नाप भूमि प्रतिकर भुगतान किया जाना है। -- as on 23-Dec-2023
Physical Peramenters