Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 10 | 7.5 | 0.000 | 7.5 | 0.000 | 0.000 |
37W111 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 1440/।।। (2)/11-05 (प्रा0आ0)/2010 दि0 28/3/2011
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
126.00
Resanction Cost :
126.00
Tentative Cost :
126.00
Exp. Upto Last Fy : 4.58
For CFY 2024-2025
Remaining : 121.42
Demand : 9.00
Allotment : 9.00
Exp in CFY : 0.00
Total Up to Date Exp : 4.58
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
13 years 3 months ago
28 Mar 2011
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 13: AIP DFO
Bottelneck: no issue
पहाड़ कटान का पूर्ण। प्रतिकर भुगतान की कार्यवाही की जानी है। -- as on 23-Dec-2023
Physical Peramenters