Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 10 | 7.5 | 0.000 | 7.5 | 0.000 | 0.000 |
37W111 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 1440/।।। (2)/11-05 (प्रा0आ0)/2010 दि0 28/3/2011
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 126.00 Lacs
Resanction Cost : 126.00 Lacs
Exp. Upto Last Fy : 4.58 Lacs
For CFY 2024-2025
Remaining : 121.42 Lacs
Demand : 9.00 Lacs
Allotment : 9.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 4.58 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
13 years 1 month ago
28 Mar 2011
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 13: AIP DFO
Bottelneck: no issue
पहाड़ कटान का पूर्ण। प्रतिकर भुगतान की कार्यवाही की जानी है। -- as on 23-Dec-2023