Work Profile Report [37W126]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 4444 (1)/।।। (2)/।।-18 (मु0मं0घो0)/2011 दिनांक 4/11/2011
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
25.20
Resanction Cost :
25.20
Tentative Cost :
25.20
Exp. Upto Last Fy :
14.18
For CFY 2024-2025
Remaining :
11.02
Demand :
1.50
Allotment :
1.00
Exp in CFY :
0.25
Total Up to Date Exp :
14.42
Alignment Approved
Sanction on : 13 years 2 weeks ago
04 Nov 2011
Physical Progress:
At start of FY 2024-2025 :
50 %
Up to Date :
50 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
वर्तमान में वन भूमि प्रस्ताव डी0एफ0ओ0 स्तर पर लम्वित। -- as on 26-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: