Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Buildings | 1 | 1 | 1 | 0 | 0 | 0 |
37W199 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 9-दो (8)/36 (2)/2014-135-दो (8)/13 दिनांक 5/11/2014
TS Amount (lakhs) : 539.84 Lacs
Financial Detail
Sanction Cost : 546.90 Lacs
Resanction Cost : 546.90 Lacs
Exp. Upto Last Fy : 517.00 Lacs
For CFY 2024-2025
Remaining : 29.90 Lacs
Demand : 6.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 517.00 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
9 years 6 months ago
05 Nov 2014
Tentative Completion date:
2 weeks 2 days from now
05 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
मूल कार्य पूर्ण, अतिरिक्त कार्य प्रगति पर है। -- as on 30-Mar-2024
Physical Peramenters