Work Profile Report [37W226]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 1154/।।।(2)/16-56 (प्रा0आ0) /2015 टी0सी0 दिनांक 29/2/2016
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : SCSP ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
51.30
Resanction Cost :
51.30
Tentative Cost :
51.30
Exp. Upto Last Fy :
0.70
For CFY 2024-2025
Remaining :
50.60
Demand :
1.00
Allotment :
1.00
Exp in CFY :
0.33
Total Up to Date Exp :
1.03
Alignment Approved
Sanction on : 8 years 8 months ago
29 Feb 2016
Physical Progress:
At start of FY 2024-2025 :
20 %
Up to Date :
20 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
वर्तमान में वन भूमि प्रस्ताव डी0एफ0ओ0 स्तर पर लम्वित। -- as on 26-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand