Work Profile Report [37W26]

खम्पाधार से अम्बेडकर ग्राम मल्ला चिड़िंगा मोटर मार्ग का निर्माण।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : 827/111(2)/ 08 /26(प्रा0आ0)/07 लो0नि0 अनु-2 देहरादून दिनांक 24/3/2008

TS Amount (lakhs) : 373.16 Lacs

Budget Financial Head : SCSP ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

294.00

Resanction Cost :

373.16

Tentative Cost :

373.16

Exp. Upto Last Fy :

370.10

For CFY 2024-2025

Remaining :

3.06

Demand :

3.06

Allotment :

8.00

Exp in CFY :

3.00

Total Up to Date Exp :

373.10

Work completed

Sanction on : 16 years 9 months ago

24 Mar 2008

Physical Progress:

At start of FY 2024-2025 :

60 %

Up to Date :

100 %

Tentative Completion date on : 1 month 3 weeks ago

01 Nov 2024

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
7
7
1.500
5.5
0.000
5.500

Remark

view all

कार्य पूर्ण, दायित्व शेष। -- as on 20-Dec-2024

Rating : 100

Forest Case Pending At : 18: Final Approval

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI:

© PWD Uttarakhand