Work Profile Report [37W26]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 827/111(2)/ 08 /26(प्रा0आ0)/07 लो0नि0 अनु-2 देहरादून दिनांक 24/3/2008
TS Amount (lakhs) : 373.16 Lacs
Budget Financial Head : SCSP ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
294.00
Resanction Cost :
373.16
Tentative Cost :
373.16
Exp. Upto Last Fy :
370.10
For CFY 2024-2025
Remaining :
3.06
Demand :
3.06
Allotment :
8.00
Exp in CFY :
3.00
Total Up to Date Exp :
373.10
Work completed
Sanction on : 16 years 9 months ago
24 Mar 2008
Physical Progress:
At start of FY 2024-2025 :
60 %
Up to Date :
100 %
Tentative Completion date on : 1 month 3 weeks ago
01 Nov 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण, दायित्व शेष। -- as on 20-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: