Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 0.000 | 0.000 |
37W260 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 2321/।।।(2)/16-05 (एम0एल0ए0) 2015 टी0सी0 दिनांक 17/8/2016
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 59.00 Lacs
Resanction Cost : 59.00 Lacs
Exp. Upto Last Fy : 0.74 Lacs
For CFY 2024-2025
Remaining : 58.26 Lacs
Demand : 1.50 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.74 Lacs
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 10 %
Sanction on :
7 years 9 months ago
17 Aug 2016
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 07: Nodal
Bottelneck: no issue
आपत्तियों का निराकरण कर डी0एफ0ओ0 को प्रेषित। -- as on 01-Mar-2024
Physical Peramenters