Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 8 | 8 | 8.000 | 0 | 0.000 | 0.000 |
37W27 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 2490/111-2/ 08-61 (प्रा0आ0)/07 दिनांक 25/7/2008
TS Amount (lakhs) : 294 Lacs
Financial Detail
Sanction Cost : 294.00 Lacs
Resanction Cost : 294.00 Lacs
Exp. Upto Last Fy : 268.78 Lacs
For CFY 2024-2025
Remaining : 25.22 Lacs
Demand : 1.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 268.78 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
15 years 9 months ago
25 Jul 2008
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 18: Final Approval
Bottelneck: no issue
कार्य पूर्ण। भूमि विवाद के कारण कुछ कास्तकारों का मुआवजा आवंटन का कार्य बाधित। -- as on 23-Dec-2023