Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 8 | 8 | 8.000 | 0 | 0.000 | 0.000 |
37W27 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 2490/111-2/ 08-61 (प्रा0आ0)/07 दिनांक 25/7/2008
TS Amount (lakhs) : 294 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
294.00
Resanction Cost :
294.00
Tentative Cost :
294.00
Exp. Upto Last Fy : 268.78
For CFY 2024-2025
Remaining : 25.22
Demand : 1.00
Allotment : 3.00
Exp in CFY : 2.56
Total Up to Date Exp : 271.34
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
15 years 11 months ago
25 Jul 2008
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 18: Final Approval
Bottelneck: no issue
कार्य पूर्ण। भूमि विवाद के कारण कुछ कास्तकारों का मुआवजा आवंटन का कार्य बाधित। -- as on 23-Dec-2023
Physical Peramenters