Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 0.000 | 2 | 0.000 | 0.000 |
No of Bridges | 1 | 1 | 0 | 1 | 0 | 0 |
Span of Bridges [m] | 30 | 30 | 0.000 | 30 | 0.000 | 0.000 |
37W297 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 1588/।।।(2)/18-05 (एम0एल0ए0) /2017 दिनांक 12/04/2018
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
28.64
Resanction Cost :
28.64
Tentative Cost :
28.64
Exp. Upto Last Fy : 4.79
For CFY 2024-2025
Remaining : 23.85
Demand : 6.00
Allotment : 6.00
Exp in CFY : 0.00
Total Up to Date Exp : 4.79
Work completed
Physical Progress:
At start of FY 2024-2025 : 95 %
Up to Date : 95 %
Sanction on :
6 years 3 months ago
12 Apr 2018
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 13: AIP DFO
Bottelneck: no issue
सैद्वातिक स्वीकृति प्राप्त, विधिवत् स्वीकृति हेतु अनुपालन आख्या प्रेषित। -- as on 23-Dec-2023
Physical Peramenters