Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 0.000 | 3 | 0.000 | 0.000 |
37W301 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 147/।।।(2)/18-05 (एम0एल0ए0) /2017 दिनांक 9/02/2018
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 41.16 Lacs
Resanction Cost : 41.16 Lacs
Exp. Upto Last Fy : 1.08 Lacs
For CFY 2024-2025
Remaining : 40.08 Lacs
Demand : 1.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 1.08 Lacs
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 25 %
Up to Date : 25 %
Sanction on :
6 years 3 months ago
09 Feb 2018
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 08: State Government
Bottelneck: no issue
वर्तमान में वन भूमि प्रस्ताव नोडल स्तर पर लम्वित। -- as on 01-May-2024
Physical Peramenters