Work Profile Report [37W302]

fवकास खण्ड नारायणबगड़ के अन्तर्गत fसमली से नाखोली तक मोटर मार्ग का fनर्माण कार्य।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : 789(अ)/।।।(2)/18-05 (एम0एल0ए0) /2017 टी0सी0 दिनांक 23/02/2018

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

38.40

Resanction Cost :

38.40

Tentative Cost :

38.40

Exp. Upto Last Fy :

1.59

For CFY 2025-2026

Remaining :

36.81

Demand :

3.80

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

1.59

Work deferred

Sanction on : 7 years 10 months ago

23 Feb 2018

Physical Progress:

At start of FY 2025-2026 :

20 %

Up to Date :

25 %

Tentative Completion date on : 1 year 2 months from now

31 Mar 2027

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
3
2.15
2.15
-
Bridge
1 (48m)
1 (48m)
1 (48m)
-

Remark

view all

उक्त मोटर मार्ग में अपर सचिव महोदय, उत्तराखंड शासन के पत्रांक संख्या -2282 / X -3 -25 /1 (55)/2025 -E -93145 में वन भूमि प्रस्ताव उप वन महानिदेशक भारत सरकार पर्यावरण , वन एवं जलवायु परिवर्तन मंत्रालय स्तर को सैद्धांतिक स्वीकृति हेतु पत्र प्रेषित Iउक्त मोटर मार्ग वर्ष 2025-26 पी0 एम0 जी0 एस 0 वाई फेज - 04 में प्रस्तावित है
-- as on 03-Dec-2025

Rating : 20

Forest Case Pending At : 09: GOI

Hindrance / Bottleneck : To Cancel

Assets :

Work not linked with IM

Bridges on The Basis of AI: