Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.5 | 1.5 | 0.000 | 1.5 | 0.000 | 0.000 |
No of Bridges | 1 | 1 | 0 | 1 | 0 | 0 |
Span of Bridges [m] | 84 | 84 | 0.000 | 84 | 0.000 | 0.000 |
37W303 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 789(अ)/।।।(2)/18-05 (एम0एल0ए0) /2017 टी0सी0 दिनांक 23/02/2018
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
30.70
Resanction Cost :
30.70
Tentative Cost :
30.70
Exp. Upto Last Fy : 13.96
For CFY 2024-2025
Remaining : 16.74
Demand : 1.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 13.96
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 10 %
Sanction on :
6 years 4 months ago
23 Feb 2018
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 01: Withdraw
Bottelneck: no issue
पुनः सर्वेक्षण कार्य पूर्ण कर लिया गया है। -- as on 03-Jul-2024
Physical Peramenters