Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 1.000 | 1 | 1.000 | 1.000 |
37W304 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 789/।।।(2)/18-05 (एम0एल0ए0) /2017 टी0सी0 दिनांक 23/02/2018
TS Amount (lakhs) : 147.82 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
147.82
Resanction Cost :
158.91
Tentative Cost :
158.91
Exp. Upto Last Fy : 141.52
For CFY 2024-2025
Remaining : 17.39
Demand : 8.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 141.52
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
6 years 4 months ago
23 Feb 2018
Tentative Completion date:
2 months 1 week from now
30 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 16-May-2024
Physical Peramenters