Work Profile Report [37W394]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 518(1)/।।।(2)/21-05(एम0एल0ए0)/2017 टी0सी0 ।। दिनांक 10/03/2021
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
35.20
Resanction Cost :
35.20
Tentative Cost :
35.20
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
35.20
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.00
Survey work done
Sanction on : 4 years 4 months ago
10 Mar 2021
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
0 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पुनः सर्वेक्षण कार्य किया जा रहा है। -- as on 05-Jul-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand