Work Profile Report [37W424]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 2572(1)/III(2)/21-05(MLA)/2017 TC
TS Amount (lakhs) : 111.41 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
111.41
Resanction Cost :
118.69
Tentative Cost :
118.69
Exp. Upto Last Fy :
72.78
For CFY 2024-2025
Remaining :
45.91
Demand :
42.00
Allotment :
37.42
Exp in CFY :
37.42
Total Up to Date Exp :
110.20
In Maintenance After Completion
Sanction on : 3 years 3 months ago
05 Aug 2021
Physical Progress:
At start of FY 2024-2025 :
60 %
Up to Date :
100 %
Tentative Completion date on : 5 months 3 weeks ago
31 May 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण, दायित्व शेष। -- as on 31-May-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: