Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 0.000 | 3 | 0.000 | 0.000 |
37W436 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 3587(1)/।।।(2)/21-05 एम0एल0ए0/2017 टी0सी0
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 41.22 Lacs
Resanction Cost : 41.22 Lacs
Exp. Upto Last Fy : 0.27 Lacs
For CFY 2024-2025
Remaining : 40.95 Lacs
Demand : 1.00 Lacs
Allotment : 1.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.27 Lacs
Survey work done
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
2 years 8 months ago
10 Sep 2021
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 04: DFO
Bottelneck: no issue
वर्तमान में वन भूमि प्रस्ताव नोडल स्तर पर लम्वित। -- as on 30-Apr-2024
Physical Peramenters