Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 2.000 | 0 | 0.000 | 0.000 |
37W438 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 3588(1)/।।।(2) 21-05 (एम0एल0ए0)2017
TS Amount (lakhs) : 44.96 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
44.96
Resanction Cost :
47.04
Tentative Cost :
47.04
Exp. Upto Last Fy : 46.57
For CFY 2024-2025
Remaining : 0.47
Demand : 0.05
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 46.57
In Maintenance After Completion
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 10 months ago
10 Sep 2021
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य दिनांक 11.12.2022 से अनुरक्षण के अन्तर्गत है। -- as on 01-Mar-2024
Physical Peramenters