Work Profile Report [37W441]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 1171/।।।(1)/2021-31 (सी0आर0आई0एफ0)/2021
TS Amount (lakhs) : 1258.19 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
1258.19
Resanction Cost :
1258.19
Tentative Cost :
1258.19
Exp. Upto Last Fy :
1,261.43
For CFY 2024-2025
Remaining :
-3.24
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
1,261.43
Construction Started
Sanction on : 3 years 1 month ago
27 Oct 2021
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
100 %
Tentative Completion date on : 8 months 3 weeks ago
31 Mar 2024
Actual Completion Date : 9 months 3 weeks ago
29 Feb 2024
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 31-Mar-2024
Assets :
Work not linked with IM
Roads on The Basis of AI: Road 1
Bridges on The Basis of AI: Garhkot paidal pul Maiduni Gadhera