Work Profile Report [37W451]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 611/D.P./2021-22
TS Amount (lakhs) : 2 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
10.00
Resanction Cost :
10.00
Tentative Cost :
10.00
Exp. Upto Last Fy :
9.94
For CFY 2025-2026
Remaining :
0.06
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
9.94
Work completed
Sanction on : 3 years 1 week ago
29 Aug 2022
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 year 5 months ago
31 Mar 2024
Actual Completion Date : 5 months 1 week ago
30 Mar 2025
Physical Linear Components
Remark
कार्य पूर्ण, दायित्व शेष। -- as on 21-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: