Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 1.000 | 2 | 1.000 | 0.650 |
37W482 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E.File No. 33931 dated 02-03-2023
TS Amount (lakhs) : 113.43 Lacs
Financial Detail
Sanction Cost : 113.43 Lacs
Resanction Cost : 121.94 Lacs
Exp. Upto Last Fy : 28.48 Lacs
For CFY 2024-2025
Remaining : 93.46 Lacs
Demand : 70.00 Lacs
Allotment : 8.95 Lacs
Exp in CFY : 9.67 Lacs
Total Up to Date Exp : 38.15 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 20 %
Up to Date : 20 %
Sanction on :
1 year 2 months ago
02 Mar 2023
Tentative Completion date:
4 months 1 week from now
30 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: Other Reason
600 मी0 लम्बाई में पहाड कटान पूर्ण।शेष पहाड़ कटान का कार्य प्रगति में है। -- as on 06-Mar-2024
Physical Peramenters