Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 1.000 | 2 | 1.000 | 1.000 |
37W482 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E.File No. 33931 dated 02-03-2023
TS Amount (lakhs) : 113.43 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
113.43
Resanction Cost :
121.94
Tentative Cost :
121.94
Exp. Upto Last Fy : 28.48
For CFY 2024-2025
Remaining : 93.46
Demand : 82.00
Allotment : 23.50
Exp in CFY : 23.25
Total Up to Date Exp : 51.72
Construction Started
Physical Progress:
At start of FY 2024-2025 : 20 %
Up to Date : 80 %
Sanction on :
1 year 4 months ago
02 Mar 2023
Tentative Completion date:
2 months 1 week from now
30 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: Other Reason
पहाड़ कटान का कार्य प्रगति में है। -- as on 14-Jun-2024