Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.25 | 4.25 | 2.500 | 1.75 | 0.000 | 1.250 |
37W483 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E.File No. 33931
TS Amount (lakhs) : 127.59 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
127.59
Resanction Cost :
137.16
Tentative Cost :
137.16
Exp. Upto Last Fy : 37.90
For CFY 2024-2025
Remaining : 99.26
Demand : 84.00
Allotment : 39.00
Exp in CFY : 38.33
Total Up to Date Exp : 76.23
Construction Started
Physical Progress:
At start of FY 2024-2025 : 25 %
Up to Date : 80 %
Sanction on :
1 year 4 months ago
02 Mar 2023
Tentative Completion date:
1 month 2 weeks from now
01 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पहाड़ कटान का कार्य प्रगति में है। -- as on 04-Jan-2024
Physical Peramenters