Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.25 | 4.25 | 2.500 | 1.75 | 0.000 | 1.250 |
37W483 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E.File No. 33931
TS Amount (lakhs) : 127.59 Lacs
Financial Detail
Sanction Cost : 127.59 Lacs
Resanction Cost : 137.16 Lacs
Exp. Upto Last Fy : 37.90 Lacs
For CFY 2024-2025
Remaining : 99.26 Lacs
Demand : 99.26 Lacs
Allotment : 10.00 Lacs
Exp in CFY : 38.33 Lacs
Total Up to Date Exp : 76.23 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 25 %
Up to Date : 25 %
Sanction on :
1 year 2 months ago
02 Mar 2023
Tentative Completion date:
4 months 1 week from now
30 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पहाड़ कटान का कार्य प्रगति में है। -- as on 04-Jan-2024