Work Profile Report [37W483]

कुलसारी-नैल-ढालू मोटर मार्ग का निर्माण। (स्टेज-।।, फेज-1)
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Nabard
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : E.File No. 33931

TS Amount (lakhs) : 127.59 Lacs

Budget Financial Head : NABARD ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

127.59

Resanction Cost :

137.16

Tentative Cost :

137.16

Exp. Upto Last Fy :

37.90

For CFY 2024-2025

Remaining :

99.26

Demand :

80.00

Allotment :

78.23

Exp in CFY :

68.23

Total Up to Date Exp :

106.13

Work completed

Sanction on : 1 year 9 months ago

02 Mar 2023

Physical Progress:

At start of FY 2024-2025 :

25 %

Up to Date :

100 %

Tentative Completion date on : 3 months 3 weeks ago

01 Sep 2024

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
4.25
4.25
2.500
1.75
0.000
1.750

Remark

view all

कार्य पूर्ण, दायित्व शेष। -- as on 05-Nov-2024

Rating : 100

No Forest Case in The Work

No Hindrance / Bottleneck