Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 25 | 17.25 | 0.000 | 17.25 | 0.000 | 17.250 |
37W485 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : पत्र सं0- 895/07याता0-पी0एम0जी0एस0वाई0-नि0 ।।। दिनांक 16.05.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
700.42
Resanction Cost :
700.42
Tentative Cost :
700.42
Exp. Upto Last Fy : 160.27
For CFY 2024-2025
Remaining : 540.15
Demand : 540.15
Allotment : 236.72
Exp in CFY : 236.72
Total Up to Date Exp : 396.99
Work completed
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 100 %
Sanction on :
1 year 2 months ago
16 May 2023
Tentative Completion date:
3 weeks 1 day ago
25 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण, दायित्व शेष। -- as on 14-Jun-2024
Physical Peramenters