Work Profile

जनपद चमोली के विधानसभा क्षेत्र थराली के अन्तर्गत थराली-कुराड़ मोटर मार्ग।


Work not linked with IM

Bridges on The Basis of AI:

Administrative Approval Detail : पत्र सं0- 895/07याता0-पी0एम0जी0एस0वाई0-नि0 ।।। दिनांक 16.05.2023

TS Amount (lakhs) : 0 Lacs

Financial Detail

Sanction Cost : 263.77 Lacs

Resanction Cost : 263.77 Lacs

Exp. Upto Last Fy : 67.70 Lacs

For CFY 2024-2025

Remaining : 196.07 Lacs

Demand : 196.07 Lacs

Allotment : 90.00 Lacs

Exp in CFY : 64.15 Lacs

Total Up to Date Exp : 131.86 Lacs

Construction Started

Physical Progress:

At start of FY 2024-2025 : 15 %

Up to Date : 15 %

Sanction on :
1 year 3 days ago
16 May 2023


Tentative Completion date:
2 weeks 1 hour ago
05 May 2024


Actual Completion Date:
Not Yet Reported


Rating : 50

Remark

Bottelneck: no issue


कार्य प्रगति में। -- as on 13-Dec-2023

Physical Peramenters

Particulars Sanction Resanction Upto Last Fy For Cfy 2024-2025
Remaining Target Achievement
Length of Road [Km] 16.89 16.89 0.000 16.89 16.890 0.000