Work Profile Report [37W486]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : पत्र सं0- 895/07याता0-पी0एम0जी0एस0वाई0-नि0 ।।। दिनांक 16.05.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
263.77
Resanction Cost :
263.77
Tentative Cost :
263.77
Exp. Upto Last Fy :
67.70
For CFY 2024-2025
Remaining :
196.07
Demand :
196.07
Allotment :
151.00
Exp in CFY :
150.96
Total Up to Date Exp :
218.66
Work completed
Sanction on : 1 year 7 months ago
16 May 2023
Physical Progress:
At start of FY 2024-2025 :
15 %
Up to Date :
100 %
Tentative Completion date on : 1 month 3 weeks ago
31 Oct 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 21-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: