Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 11.95 | 11.95 | 0.000 | 11.95 | 0.000 | 0.000 |
37W487 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : पत्र सं0- 895/07याता0-पी0एम0जी0एस0वाई0-नि0 ।।। दिनांक 16.05.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 208.86 Lacs
Resanction Cost : 208.86 Lacs
Exp. Upto Last Fy : 38.20 Lacs
For CFY 2024-2025
Remaining : 170.66 Lacs
Demand : 170.66 Lacs
Allotment : 60.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 38.20 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 15 %
Up to Date : 15 %
Sanction on :
1 year 3 days ago
16 May 2023
Tentative Completion date:
1 week 5 days ago
07 May 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति में। -- as on 13-Dec-2023
Physical Peramenters