Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 6.01 | 6.01 | 0.000 | 6.01 | 4.000 | 0.000 |
37W488 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : पत्र सं0- 895/07याता0-पी0एम0जी0एस0वाई0-नि0 ।।। दिनांक 16.05.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 125.22 Lacs
Resanction Cost : 125.22 Lacs
Exp. Upto Last Fy : 14.92 Lacs
For CFY 2024-2025
Remaining : 110.30 Lacs
Demand : 110.30 Lacs
Allotment : 60.00 Lacs
Exp in CFY : 18.55 Lacs
Total Up to Date Exp : 33.48 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 10 %
Sanction on :
1 year 3 days ago
16 May 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति में। -- as on 01-Mar-2024
Physical Peramenters